Sports Court Lighting Installation: Foundations, Cabling, Aiming and Commissioning, Step by Step

How sports court floodlights are installed: pole foundations, cable sizing, mounting, aiming and the commissioning light-level check, with a voltage-drop calculation for a 6-pole tennis court.

Key points

  • A court lighting job runs in a fixed order: design and approvals, foundations, ducts and cable, poles, floodlights, aiming, then a measured light-level check.
  • Our published layout for one tennis court is 18 BG-TZ-M floodlights of 150 W on 6 poles of 8–10 m for 200 lux; split into two 3-pole circuits, each draws about 6 A at 230 V.
  • For a farthest pole 66 m from the board, voltage drop on 2.5 mm² copper is about 2.4%, on 4 mm² about 1.5% and on 6 mm² about 1.0%.
  • Aiming is done at night or with an aiming tool to the angles in the design, and locked; most complaints about glare and dark patches come from aiming done by eye.
  • Commissioning means measuring illuminance on a grid and comparing the average and uniformity with the design and the EN 12193 class.

A good lighting design can be ruined on site. Foundations in the wrong place shift the poles, undersized cable dims the far floodlights, and aiming by eye throws light into neighbours’ gardens and leaves dark corners on the court. This guide sets out the installation in the order it should happen, with the electrical numbers for a typical tennis court using our own floodlights.

Step 1: design, survey and approvals

Before anyone digs, the design should fix:

  • Court size including run-off, and the sport and level of play
  • Pole positions, heights and foundations
  • Number, wattage and aiming angle of every floodlight
  • Expected average illuminance and uniformity
  • Supply: where the board is, what capacity is available

For a single tennis court, our published layout uses 18 of our BG-TZ-M modular sports floodlights at 150 W on 6 poles of 8–10 m for about 200 lux recreational play, or 21 at 200 W for 300 lux club play.

Planning permission is often needed for poles and floodlights, especially near homes. Councils may set curfew hours and spill limits. Survey for buried services and check ground conditions at each pole position.

Step 2: foundations

Pole foundations are designed for the pole height, the floodlight load and the local wind speed. Typical options:

  • Pad foundation with a cast-in anchor bolt cage, for flange-plate poles
  • Bored pile, where space is tight or ground is soft
  • Planted pole, set directly in a concrete-filled hole

Set anchor bolts with the template supplied with the pole, at the right height and orientation so the pole door faces where it can be reached. Cast ducts into each foundation for the supply cable. Allow the concrete to reach strength before erecting poles.

Step 3: ducts and cable

Lay ducts from the board to each pole with draw pits at turns and long runs. Pull the cable once ducts are in, and leave spare length in each pole.

Cable size worked out

The 18 × 150 W floodlights total 2.7 kW. Splitting the court into two circuits, one per long side, gives 3 poles and 1,350 W per circuit. With the BG-TZ-M’s power factor above 0.97 at 230 V:

1,350 ÷ (230 × 0.97) = about 6.05 A per circuit.

Assume the board is 30 m from the first pole and the poles stand at 0, 18 and 36 m along the side, so the farthest pole is 66 m away. Putting the whole load at the farthest pole (which overstates the drop), with copper at 0.0175 Ω·mm²/m:

Cable Voltage drop Share of 230 V
2.5 mm² 5.6 V 2.4%
4 mm² 3.5 V 1.5%
6 mm² 2.3 V 1.0%

All three meet a typical 3% lighting limit, but 4 mm² leaves margin for a longer run or a later upgrade to 200 W heads. Use three-phase supply on larger installations to balance the load.

Step 4: poles and floodlights

Assemble floodlights and cross-arms on the ground where possible; working at height takes longer and costs more.

  1. Fit floodlights to the cross-arm with the brackets and hardware supplied.
  2. Wire each floodlight to the junction box at the pole top, with drip loops so water runs off before cable entries.
  3. Lift the pole by crane and set it on the anchor bolts; plumb it with levelling nuts.
  4. Pull the supply cable into the pole, terminate in the base compartment with fuses or a breaker for each pole.
  5. Fit surge protection where storms are common.

Step 5: aiming

Each floodlight has a design aiming point and tilt. Our BG-TZ-M uses an asymmetric 140° × 80° beam with a 30° offset, so the glass is tilted less than the aiming angle and stays nearly flat. That reduces glare, but only if the tilt matches the design.

  • Use the angle scale on the bracket or a digital inclinometer, not judgement by eye.
  • Aim at night with a target marker on the court if possible.
  • Tighten and mark the bracket position so it can be checked later.

Step 6: commissioning

Commissioning proves the installation does what the design said.

  1. Run the lights for long enough that output is stable.
  2. Mark a grid of measuring points over the court, at the spacing the standard or the design specifies.
  3. Measure illuminance at each point with a calibrated lux meter held level, with no shadow from the person measuring.
  4. Calculate the average, the minimum, and the uniformity (minimum ÷ average).
  5. Compare with the design and with the EN 12193 class.
  6. Check spill at the boundary if planning conditions require it.

Record the results with the date, meter and weather. They become the baseline for later checks; LED output falls slowly over the years, and a measured baseline shows when cleaning or adjustment is due.

Step 7: handover

Hand over the as-built drawings, aiming schedule, test results, circuit list, warranty documents and a simple instruction for the switching or controls. If the court has a timer or booking-linked control, set it with the owner.

Electricians and service contracts

Clubs and schools often ask for a single contractor to install and maintain the lights. A service visit once a year to check fixings, clean glass, test the RCD and re-measure a few points keeps the lighting at its design level. Our guide to sports court lighting repair and replacement covers the decision when old installations fail, and tennis court lighting covers the standards in more depth.

For other courts, our padel court lighting and basketball court lighting guides give pole layouts; our pole height and spacing calculator helps with surrounding paths and car parks.

Before you order

Send us the court plan, the sport and level, the pole positions you can use and the distance to the board. We will return a floodlight layout, aiming schedule and the electrical load for your contractor, and supply flood lights to match.

Sources

  1. CEN — EN 12193 Light and lighting, sports lighting
  2. BlueGreen OE — Modular LED sports floodlight BG-TZ-M
  3. BlueGreen OE — Pole height and spacing calculator

Frequently asked questions

How long does it take to install court lighting?

For one court, the foundations take a day or two to dig and pour, then need time to cure. Poles, floodlights, cabling and aiming typically take a few more days. Approvals and delivery usually take longer than the site work.

Who installs sports court lighting?

A licensed electrical contractor for the supply and cabling, a civil contractor or the electrician's team for foundations, and a crane or lift for the poles. The lighting supplier provides the design, aiming angles and often site support.

What cable size is used for tennis court lights?

It depends on the load and distances. In our 6-pole example, 4 mm² copper keeps voltage drop to about 1.5% for each 3-pole circuit; long runs from the board may need 6 mm² or more.

How do you check court lighting after installation?

Measure illuminance with a calibrated lux meter on a grid of points across the court at night, then calculate the average and the ratio of minimum to average, and compare them with the design.

Products in this guide

Have a project?

Ask our engineers

Send us your site details and we will size the system and quote it.

We reply by email within one working day (China time, GMT+8). Your details are only used to answer this inquiry. Prefer chat? Message us on WhatsApp. Have more detail to give? Use the full form.

Related guides